COMPLETED PROJECTS
Introduction to our services... a specialist sub contractor to the civil engineering industry with over 20 years experience. We always welcome new clients. Call us or send an email with your enquiry for an immediate response.FEATURED PROJECT - SLEAFORD SLIPWAY
SCOPE: Re-profile and excavate existing riverbank. Install plastic pile and new coping and slipway. Remove existing pathway and replace with new brick and block pathway in new location.
ISSUES: This is a high profile site in the centre of Sleaford surrounded by trees subject to preservation orders.
-
GANNY LOCK AT BRIGHOUSE
Galliford Try, project managers for British Waterways' Omnibus II scheme, called in drilling experts Condor Projects to help keep the waterway up and running and the lock at Brighouse open.
-
BRITISH WATERWAYS
SCOPE: Grout curtain, sheet piling wall, new copings, Cray fish baskets
ISSUES: The site adjacent to the canal was being developed and there was a leak from the canal onto the site. Condor was asked to install a grout curtain to stop the leak and then install a 100m sheet pile wall as well as design, manufacture and install new coping stones and Cray fish baskets
-
SLIPWAY
Project: Install a grout curtain
and pressure point Client: Dew Construction / British Waterways
-
BANK STABILISATION
SCOPE: Bank stabilisation
ISSUES: All the work had to be undertaken whilst the householders were living in the cottage. The slope was steep, unstable and ran directly to a canal.